Construction Progress Report - January 2009

Construction update images of Saunton Sands

We are pleased to report that the programme is being maintained and that motivation remains high as the project progresses towards the beginning of phase 2.

We are finalising formal arrangement to accept phase one works from G2 project solutions.

The blockwork to the main frame is now complete and the planks have now been placed.

We are preparing the site for the initial wall panels of the timber frame to be delivered within the next two weeks.

The masons are completing the final elements of stone work to balcony's at level -2 and -1.

Snagging inspections on the lower two floors are complete and a CCTV survey of the new drainage testing has been undertaken.